Return to Headlines

School Bond Construction Update

Here are updated pictures from the School Bond Construction projects underway right now.   Athletic facilities and classroom additions are on track to be ready for the 2019-2020 school year.  New Middle School on track to be ready for the 2020-2021 school year.

 

Town Creek Middle School Construction: (October, 2019)
Bird's Eye View!

Town Creek Middle School

Town Creek Middle School

Town Creek Middle School

 

 

Town Creek Elementary Six Classroom Addition: (June, 2019)
New furniture has arrived!

 

Town Creek Elementary

Town Creek Elementary

Town Creek Elementary

Town Creek Elementary

Town Creek Elementary

Town Creek Elementary

 

Town Creek Middle School Construction (May, 2019)

 

Town Creek Middle School

 

Town Creek Middle School

 

Town Creek Middle School

 

Town Creek Elementary Six Classroom Addition: (May, 2019)

A temporary Certificate of Occupancy (CO) was issued May 28th. An established stand of grass is required for the final CO.

 

Town Creek Elementary

 

Town Creek Elementary

 

Town Creek Elementary

 

Lincoln Elementary School Six Classroom Addition: (May, 2019)

 

LES addition

LES addition 2

LES Addition 3

 

Town Creek Middle School construction: (May, 2019)

 

TCMS

TCMS 2

TCMS 3

TCMS 4

 

Town Creek Elementary School Six Classroom Addition: (May, 2019)

 

TCES addition

 

South Brunswick High School Fieldhouse construction: (May, 2019)

 

SBHS Fieldhouse

SBHS Fieldhouse 2

 

North Brunswick High School Fieldhouse construction: (May, 2019)

 

NBHS Fieldhouse

NBHS Fieldhouse 2

NBHS Fieldhouse 3

 

New Lighting at all the high schools: (May, 2019)

 

New lighting

New lighting 2

New lighting 3

 

Town Creek Middle School construction:  (April, 2019)

Town Creek Middle construction

 

 

New interior photos of Town Creek Elementary's 6 classroom addition: (2/21/2019):

Interior of Town Creek Elementary 6 class addition

 

Interior of Town Creek Elementary 6 class addition

 

New playground equipment at Bolivia Elementary photos:

 

Playground at Bolivia Elementary

 

Playground at Bolivia Elementary

 

North Brunswick High School Fieldhouse construction photos:

 

North Brunswick Fieldhouse

 

North Brunswick Field house construction

 

North Brunswick Field House

 

North Brunswick Soccer Field House

 

Lincoln Elementary 6 classroom addition photos:

 

Lincoln Elementary 6 classroom addition

 

Lincoln Elementary 6 classroom addition

 

Lincoln Elementary 6 classroom addition

 

Lincoln Elementary 6 class addition

 

South Brunswick High School Fieldhouse construction photo:

 

South Brunswick Field house construction

 

South Brunswick Field House

 

 

Town Creek Elementary: 

 

Town Creek Elementary

The six classroom addition project is on schedule to open to students in the Fall of 2019.

Construction of the addition is ongoing with structura steel, exterior wall studs and sheathing, roof decking, and the mechanical mezzanine installed.  Work continues on the interior electrical and mechanical rough-ins.

 

 

Town Creek Elementary

 Click here to see more photos.

 

Town Creek Middle

The new school project is on schedule for 2020 completion.

 

Town Creek Middle

 

Town Creek Middle

 

Town Creek Middle

 

The storm-water pond is installed with site, fire hydrants and sanitary sewer nearing completion.  Building foots are approaching 50% and wall construction in the gym area in ongoing.  Paving sub-base is being installed on selected parking and traffic areas to support emergency vehcile access around the building.

 

Town Creek middle

 Click here to see more photos.

 

Lincoln Elementary: 

The six classroom addition project is on schedule for 2019 completion.

The storm-water pond is complete with site storm-water piping 50% complete.  Phased work continues with footings, undergound plumbing and the concrete slab completed in the swection of the addition that ties into the c-wing.  Work continues on completing the footings and remainder of the concrete slab.  Required changes associated with the new water and sanitary tie-ions to infra-structure are under engineering review.

 

Lincoln Elementary Update

 Click here to see more photos.

 

Athletic Improvements: 

Construction of the new athletic buildings at NBHS and SBHS are progressing.  At NBHS, floor slabs, load bearing walls, roof steel and decking are complete at the wrestling and weight room additions and brick veneer has started.  Stell erection is 50% complete at the field house.  Reword of the NBHS football field will begin late Jan/Early Feb.  At SBHS, progress at the wrestling room is similar to that of NBHS.  Masonry walls at the field house are 50%.

 

South Brunswick High:  

The athletic field house project is on schedule for April, 2019 completion.

 

South Brunswick High Update

 South Brunswick High

Click here to see more photos. 

 

North Brunswick High:  

The athletic field house project is on schedule for April, 2019 completion.

 

North Brunswick High Update

 

New lighting at the SBHS and WBHS baseball fields is almost complete and work at the NBHS football and softball fields is continuing.

 

New playground equipment has been installed or is in progress at 4 of the elementary schools, equipment has been ordered at others and equipment selection is in process at the last.  The landscape architect has visited all schools and generated site plans delineating landscaping activities to include the removal of damaged or deficient plantings and the planting of native vegetation that does not cause security issues and is low maintenance. 

 

Exciting times are ahead and construction projects are in full swing with the 2016 Bond Referendum authorized projects.