School Bond Construction Update

Here are the latest updates from the School Bond Construction projects underway right now.

 

Town Creek Elementary: 

The six classroom addition project is on schedule for a June, 2019 completion.

Work continues to support the pouring of the floor slab the week of October 29. Steel has been delivered.

 

Town Creek Elementary

 Click here to see more photos.

 

Town Creek Middle

The new school project is on schedule for a May, 2020 completion.

Earthquake Wells are installed. Parking lot and road grading continues.

 

Town Creek middle

 Click here to see more photos.

 

Lincoln Elementary: 

The six classroom addition project is on schedule for June, 2019 completion.

Work continues on building footings and installation of the storm-water system.  

 

Lincoln Elementary Update

 Click here to see more photos.

 

South Brunswick High:  

The athletic field house project is on schedule for April, 2019 completion.

Work on the field house  under-slab utilities continues. At the wrestling room additions, walls are up and the roof is installed.

 

South Brunswick High Update

 South Brunswick High

Click here to see more photos. 

 

North Brunswick High:  

The athletic field house project is on schedule for April, 2019 completion.

Work at the field house and soccer field house is focusing on getting the under-slab utilities done to support pouring of the floor slab the week of 10-29. At the wrestling/weight room additions, walls are up and the roof is installed.

 

North Brunswick High Update

 

Exciting times are ahead and construction projects are in full swing with the 2016 Bond Referendum authorized projects.