School Bond Construction Update
Here are updated pictures from the School Bond Construction projects underway right now. Athletic facilities and classroom additions are on track to be ready for the 2019-2020 school year. New Middle School on track to be ready for the 2020-2021 school year.
Town Creek Middle School Construction: (October, 2019)
Bird's Eye View!
Town Creek Elementary Six Classroom Addition: (June, 2019)
New furniture has arrived!
Town Creek Middle School Construction (May, 2019)
Town Creek Elementary Six Classroom Addition: (May, 2019)
A temporary Certificate of Occupancy (CO) was issued May 28th. An established stand of grass is required for the final CO.
Lincoln Elementary School Six Classroom Addition: (May, 2019)
Town Creek Middle School construction: (May, 2019)
Town Creek Elementary School Six Classroom Addition: (May, 2019)
South Brunswick High School Fieldhouse construction: (May, 2019)
North Brunswick High School Fieldhouse construction: (May, 2019)
New Lighting at all the high schools: (May, 2019)
Town Creek Middle School construction: (April, 2019)
New interior photos of Town Creek Elementary's 6 classroom addition: (2/21/2019):
New playground equipment at Bolivia Elementary photos:
North Brunswick High School Fieldhouse construction photos:
Lincoln Elementary 6 classroom addition photos:
South Brunswick High School Fieldhouse construction photo:
Town Creek Elementary:
The six classroom addition project is on schedule to open to students in the Fall of 2019.
Construction of the addition is ongoing with structura steel, exterior wall studs and sheathing, roof decking, and the mechanical mezzanine installed. Work continues on the interior electrical and mechanical rough-ins.
Click here to see more photos.
Town Creek Middle:
The new school project is on schedule for 2020 completion.
The storm-water pond is installed with site, fire hydrants and sanitary sewer nearing completion. Building foots are approaching 50% and wall construction in the gym area in ongoing. Paving sub-base is being installed on selected parking and traffic areas to support emergency vehcile access around the building.
Click here to see more photos.
Lincoln Elementary:
The six classroom addition project is on schedule for 2019 completion.
Click here to see more photos.
Athletic Improvements:
Construction of the new athletic buildings at NBHS and SBHS are progressing. At NBHS, floor slabs, load bearing walls, roof steel and decking are complete at the wrestling and weight room additions and brick veneer has started. Stell erection is 50% complete at the field house. Reword of the NBHS football field will begin late Jan/Early Feb. At SBHS, progress at the wrestling room is similar to that of NBHS. Masonry walls at the field house are 50%.
South Brunswick High:
The athletic field house project is on schedule for April, 2019 completion.
Click here to see more photos.
North Brunswick High:
The athletic field house project is on schedule for April, 2019 completion.
New lighting at the SBHS and WBHS baseball fields is almost complete and work at the NBHS football and softball fields is continuing.
New playground equipment has been installed or is in progress at 4 of the elementary schools, equipment has been ordered at others and equipment selection is in process at the last. The landscape architect has visited all schools and generated site plans delineating landscaping activities to include the removal of damaged or deficient plantings and the planting of native vegetation that does not cause security issues and is low maintenance.
Exciting times are ahead and construction projects are in full swing with the 2016 Bond Referendum authorized projects.